Down The Shore: Bulkheads Repair in Avalon
Wednesday, March 24, 2021
The Borough of Avalon will be replacing two complete bulkheads, and fixing a small section of a third bulkhead in March-April, 2021. The project was authorized by Avalon Borough Council and will be conducted by Channel Marine. The municipal bulkheads at 22nd and 26th streets will be replaced; a small section of the bulkhead at 80th Street will be repaired. Here is the estimated construction schedule provided by the contractor:
22nd Street Bulkhead: Begin work 3/10/21; Estimated completion 3/24/21
26th Street Bulkhead: Begin work 3/31/21; Estimated completion 4/21/21
80th Street Bulkhead: Begin work 4/22/21; Estimated completion 4/28/21